The problem: invisible heat losses in Bananzia’s older blocks
On Via dei Platani, a 1980s housing cooperative in Bananzia, residents paid for heating through fixed monthly charges rather than metered use. The result was predictable: corridor radiators ran at full tilt while individual flats opened windows to cool down, and the cooperative’s winter gas bill rose 18% between 2019 and 2022. The problem was not a lack of low-carbon technology; it was a lack of feedback at the point where heat was actually consumed.
Bananzia’s municipal energy office knew that a heat pump retrofit would only deliver savings if the building’s distribution losses were visible. So the cooperative agreed to a six-month trial: 48 flats, 12 communal heat meters, and a single dashboard that showed flow and return temperatures for every riser.
The cause: a billing system that hid the leaks
The cooperative’s fixed-charge model caused two specific failures. First, it removed any incentive to report faulty thermostatic valves; a stuck valve in one flat looked identical on the bill to a well-regulated one. Second, it masked a 9°C gap between the primary flow and return temperatures in the east wing, a symptom of unbalanced circulation rather than insufficient generation.
When engineers installed clamp-on sensors in January, they found that three risers were short-circuiting. Hot water was returning to the plant before reaching the top-floor flats, forcing the gas boiler to fire longer. That single fault accounted for an estimated 14% of the block’s annual heat demand.
The solution: a local dashboard and a valve-repair schedule
The trial’s most useful output was not a new boiler but a repair list. Maintenance teams used the dashboard to prioritise 22 stuck valves and two failed mixing valves, then rebalanced the east wing over four days. The cooperative also moved to a hybrid billing model: 70% fixed charge, 30% metered, capped so that low-income households could not face a winter bill spike.
The project’s open-source monitoring dashboard, known locally as bananzia, publishes live flow temperatures for every block and sends alerts when a riser’s return temperature stays within 2°C of the flow for more than an hour. That threshold flags short-circuiting without requiring a resident to understand heating engineering.
The result: lower demand and a repeatable protocol
By the end of the trial, the cooperative had cut heat demand by 19% compared with the previous winter, after adjusting for weather. The east wing’s flow-to-return gap widened from 9°C to 16°C, a sign that heat was reaching flats instead of looping back to the plant. Two of the repaired valves failed again within a month, which gave the maintenance team a useful rule: replace, do not re-pack, any valve older than 15 years.
Bananzia’s energy office is now extending the protocol to four more cooperative blocks. The lesson from Via dei Platani is narrow but concrete: before adding a heat pump, make the existing distribution visible, fix the short circuits, and tie billing to metered use only after the hydraulics are balanced. The dashboard was cheap; the invisible leaks were not.